Use approved ESD procedures to prevent damage.
to Local (down). This will prevent
the rack from being unexpectedly powered up by the management
console (or remote
power control if the feature is installed). See Figure 1. 

to the left of the gate and at the
bottom of the storage enclosure chassis might need to be removed to
allow the gate to swing open. Remove the two screws
that fasten the baffle to the 19"
rack mount vertical rails. If the baffle is the new level sheet metal,
it has a flexible plastic cutout that bends out of the way when the
gate is swung open. 
and open the 208VDC bus bar gate to
the service position
. 
to Off (down). See Figure 5.
. See Figure 5. 
securing the mainline power cable
to PPS-2
(lower PPS).
See Figure 6.
. See Figure 6. 
and swing open the rack operator panel
. See Figure 7.
and remove the door latch bracket
. See Figure 7. 
that fasten the PPS-1 chassis
to the rack. See Figure 8. 

and then push the PPS chassis
in fully. See Figure 10.
securing the PPS to the
sheet metal tray. See Figure 10. 
about 5 cm (2 inches) further on the
sheet metal tray as shown. (This will give more clearance at the back
of the PPS for
the next step.) See Figure 11. 
. See Figure 12.
, and then remove it. See Figure 12. 
securing each end of each lower tie
bar and remove the tie bars
. See Figure 13. 
(if installed) in the lower half of
the rack. See Figure 14. 
, fiber channel interface card
and FC-AL cable
must be in the exact same position
when reinstalled in later steps. See Figure 15.
from the two fiber channel interface
cards (FCIC)
. Squeeze the top of the FC-AL cable
connector to release it from the FCIC card. See Figure 15.
fastening the storage enclosure to
the rack mount rails. See Figure 15. 
connect to the front 5/12V secondary
bus bar A. The rear storage enclosure cables
connect to the front 5/12V secondary
bus bar B.