The UEPO switch can be replaced while the storage facility is
operational, even when one side of the switch or the wires that connect
that side to a primary power supply are defective.
Non-concurrent, storage facility will
be powered off, go to MAP2180 Section-3.
MAP2180 Section-2
Before you begin
Do not disconnect the UEPO switch cable connector at J4 on
the back of either PPS until
instructed.
About this task
This procedure will not test the ability of the new UEPO
switch to actually power off the storage facility. Instead
it will check that the new UEPO switch contacts do open before it
is connected to the PPS.
Procedure
Use a volt/ohm meter to check the continuity of the new
FRU between the two pins on the cable connector that would plug to
the PPS J4
connector. With the switch in the closed position, the continuity
should be less than 0.1 ohm. With the switch in the open position,
the continuity should be infinite. Ensure both cables connectors checkout
correctly before you continue.
The next steps show and describe the
Model 94x. The 95x is similar.
At the front of the rack, remove the two rack
operator panel screws 1 . See Figure 1.
Figure 1. Rack operator panel LED assembly
WARNING: Open the rack operator panel gently.
Do not force it!
Note: A few racks built before September
2007 may have the cable to the UEPO switch installed without enough
free play. Forcing the panel open could cause the cable to break the
UEPO switch.
At the rear of the operator panel, remove the
four screws (two in front and two on the left side) that hold the
rear sheet metal cover that blocks access to the rear of the UEPO
switch.
Remove the two screws fastening the UEPO switch
to the operator panel and remove the UEPO switch. Temporarily leave
the switch assembly hanging by its wires. Ensure it does not contact
any exposed circuits. The old UEPO switch assembly and its associated
cables will be removed later in the procedure.
Observe the "top" label on the UEPO switch
and ensure it is facing up. (There are two versions of the switch,
one that has the wires connected to the bottom four pins, the other
connecting to the top four pins. The "top" label ensures it is
installed in the correct orientation.) Mount the new UEPO switch assembly
on the front cover with the "top" label facing up.
Mount the new UEPO switch assembly to the operator
panel.
Ensure the new UEPO switch setting is ON (up).
Note: To set the UEPO switch up, some service representatives
use a key to push up through the front to set the UEPO switch to on.
Route but do not connect the UEPO switch assembly
cables to the appropriate primary power supply.
Observe the UEPO LOOP GOOD LED indicator on the front of
both PPSs.
Find the condition that applies:
Make a connection to PPS-2 by performing
the following steps.
Use the utilities at the management
console to select
System Level Deactivate for PPS-2.
Switch off the PPS-2 power input circuit breaker.
Unplug the UEPO cable connected to the PPS-2 connector
J4.
Connect the cable from the new UEPO switch assembly.
Switch on the PPS-2 power input circuit breaker.
Ensure the "UEPO LOOP GOOD" LED indicator is now on.
Use the utilities at the management
console to select
System Level Activate for PPS-2.
Find the condition that applies:
The new UEPO switch has been connected to both PPSs. Go
to the next step.
The new UEPO switch has not yet been connected to PPS-1. Go
to step 12.
The new UEPO switch has not yet been connected to PPS-2. Go
to step 13.
Remove the old UEPO switch assembly.
Complete the routing for the new cables. Ensure
the cable at the operator panel has enough free play before installing
the cable retention hardware.
MAP2180 Section-3
Procedure
Power off the storage facility.
Switch off the PPS-1 and PPS-2 power input circuit breakers.
Observe the "top" label on the UEPO switch and
ensure it is facing up. (There are two versions of the switch, one
that has the wires connected to the bottom four pins, the other connecting
to the top four pins. The "top" label ensures it is installed in the
correct orientation). Replace the UEPO switch assembly. Refer to Exchange the PPS to rack operator panel UEPO cable and switch assembly.
Set the UEPO switch to on.
Switch on the PPS-1 and PPS-2 power input circuit breakers.
Observe the UEPO Loop Complete LED on PPS-1 and PPS-2.
Are both LEDs lit?
No, at the PPS with
the LED off, unplug the UEPO switch cable from the PPS connector
J4. Go to the next step.
Use a volt/ohm meter to check the continuity between the
two pins on the cable connector that is unplugged from the PPS J4 connector.
With the switch in the closed position (UEPO not active), the continuity
should be less than 0.1 ohm. Is the continuity less than 1 ohm in
the closed position?
Yes, the UEPO switch assembly is working. The PPS has a
failure of the LED or the UEPO circuit. Set the UEPO switch to the
normal position and attempt to power on. If the PPS powers
on, the LED is failing. If the PPS does
not power on, the PPS is failing
and should be replaced.
No, the UEPO switch is failing and needs to be replaced.
Set the UEPO switch to active. Observe
the UEPO Loop Complete LED on PPS-1 and PPS-2. Are both LEDs off?
Yes, the UEPO circuits are working properly. Go to step 9.
No, the UEPO switch is failing to open the UEPO loop circuit.
Go to MAP2180 Section-2 to replace
the UEPO switch assembly.
Set the UEPO switch back to the normal
operational state. Start the power to the storage facility and
when it is ready, return it to customer use.