Before you begin
If you have questions about floor loading and
service clearances of the racks, review the installation site requirements
in the
IBM® DS8870 Introduction and Planning Guide which
is available on the
IBM DS8000 series
Service Documents CDROM.
About this task
DANGER
HEAVY EQUIPMENT -- PERSONAL
INJURY OR EQUIPMENT DAMAGE MAY RESULT IF MISHANDLED (D006)
Procedure
- Verify that the new location meets the
necessary service clearances for the storage facility, which include
any attached racks. See the installation site requirements for the DS8000® in IBM DS8870 Introduction and Planning Guide.
- Do you have more than one rack to install?
- Yes, continue at the next step.
- No, go to step 4.
- You must ensure that each expansion rack is installed to
the base rack (Rack-1) that it was originally configured with.
Note: If expansion racks for two storage facilities are accidentally
intermixed, a successful installation will not be possible.
- Each rack has a small label
with its rack S/N above the front
or rear cover latch release. See Figure 1.
- Each rack has a large label
with its rack number (position in
the storage facility) and the S/N of the Rack-1 it must be installed
to. The label is to the left of the UEPO switch inside the front cover.
See Figure 1.
Note: Rack-1
large label is normally left blank.
Figure 1. Rack serial number and rack
number labels (Models 951, 95E)
- Move Rack-1 to its permanent location. If installing
on a raised floor, position the rack so the rear tailgate, especially
the rightmost opening for the mainline power cables, is directly over
the floor tile cutouts.
Note: If the storage facility is configured
for overhead cable management (top exit), floor tiles with cutouts
might not be required. Refer to
Checking customer preparations.
- Install the wheel chocks
(located in the ship group) on all
four casters. See Figure 2. Figure 2. Wheel (wedge) chocks
- Open the front cover.
- Open the left rear cover (customer access
area).
Note: On some models, the rack machine type, model,
serial (MTMS) label is located on the left rear cover, just above
the door latch. If the left rear cover is removed from the rack,
ensure it is reinstalled on the correct rack. If this is not done,
the incorrect MTMS will be displayed on the exterior of the rack,
which could result in maintenance errors or other issues. If a reference
is needed, the correct rack MTMS is also shown on the "1S" label,
affixed to the upper left inside wall of both the front and rear of
the rack.
- Open the right rear cover (trained service personnel access
area only). Use a 3 mm hex wrench to remove the two screws
. See Figure 3. Note: The screws must be reinstalled when the cover is closed
to prevent customer access.
Figure 3. Removing retaining
screws on right rear machine cover
- To access the rear of the PPS,
unfasten
and then rotate the upper and lower
sets of power distribution units (PDUs) away from the rear of the
PPS, as shown in Figure 4. Figure 4. Power distribution units in normal position (rack rear view)
- Remove the tailgate frame bracket. Remove two screws
as shown in Figure 5. Loosen but do not remove
the two top screws
. Slide the bracket out. This allows
you access to the tailgate cable retention hardware when you install
cables later in this installation. Figure 5. Tailgate frame
bracket
- Does the rack have an upper "funnel" bracket 2 at
the rear upper left of the rack? See Figure 6.
- Yes, go to the next step.
- No, go to step 15.
Figure 6. Removing top tailgate cover
plate
- Looking down at the top left rear of the rack,
inspect the top tailgate cover plate screw 3 .
See Figure 6.
- If the screw is installed from the top (only screw head is
visible), go to the next step.
- If the screw is installed from inside the rack, (only threaded
end is visible) to go step 14.
- The screw is installed from the top of the rack.
Install the screw from inside the rack and then install the top tailgate.
- Remove and discard the nut 1 securing
the upper "funnel" bracket 2 of
the host cable channel. See Figure 6.
- Remove the long screw 3 from
the top of the rack.
- Install the long screw 3 from
inside the rack. The threaded end of the screw extends out the top
of the rack.
- At the top of the rack, remove the three screws that
secure the cover plate to the top of the rack. Remove the cover plate.
- Store the cover plate in the document enclosure at the
front upper left of the rack.
- Position the tailgate assembly over the opening at the
top of the rack. See Figure 7.
Secure the assembly with the three screws that were removed in step
d.
- Go to step 15.
- The
screw is installed from inside the rack. Install the top tailgate.
- Looking down at the top of the rack, remove the three
screws around the opening for the funnel bracket. See Figure 6. The rack was shipped
with the cover plate already removed and stored in the document enclosure
at the front upper left of the rack.
- Position the tailgate assembly over the opening at the
top of the rack. See Figure 7.
Secure with the three screws that were just removed.
- Go to the next step.
- Remove the tailgate frame bracket
for Rack-3 (if present) and Rack-4 (if present) only if they do not
have the" top exit" cable feature for the mainline power cables.
- Continue at the next section.