DS8000 Service Documentation Version 7.5
Checking customer receptacle voltage pins with customer CB
on (plug in)
Procedure
- Remove
the lockout tag and/or device that was applied to each customer mainline
AC voltage circuit breaker, then switch on the customer circuit breaker.
- Prepare the multimeter to read line voltage AC.
DANGER
Dangerous voltages may be present. Do not touch the
internal parts (pins and connectors) of the customer receptacle.
- If installing 3 phase power, measure the voltage between
the ground pin and each voltage pin ( A , B ,
and C ) on the customer outlet. Refer
to Figure 2 for the location
of the voltage pins.
Are the voltages within 10% of
each other?
- Yes, continue with the next step.
- No, inform the customer that the voltages are not correct. Do
not continue until the voltages are correct.
- Locate the agency label on the inside
front left wall of the rack, halfway from the top (near the front
of PPS E2). See Figure 1.
The label will include the voltage, current, and phase specifications
for this model. Measure the voltage between each pair of voltage
pins (for three phase A to B , B to C ,
and C to A or for single phase A to B )
on the customer outlet. Refer to Figure 2 or Figure 3 for
the location of the voltage pins. Verify that the customer AC input
voltage that you just measured matches the machine input voltage information
on the label.
Do the voltages correspond with the label?
Figure 1. Agency label example (2421-941,
3-phase), with location
Figure 2. Measuring voltage between each
pair of pins
Figure 3. Single phase,
voltage pins